Minutes from 29 Mar 2006 SWMD Telephone Meeting

Present: Jonny Smith, Justin Greenhalgh, Nigel Watson
Minutes: Nigel

Notes from previous meeting

  1. Material damage

  2. Wakefield simulations:
    GdfidL output for cylindrically symmetric jaws
    1. Summary of pbx runs
    2. Summary of pbxb runs
    3. Runtime durations

    Jonny described the detailed studies he has carried out on sensitivity of his loss factor simulations to input parameters such as no. of mesh cells per sigma_z, aspect ratio of the mesh, and bunch length, using as example the pill box cavity. Discussed for transverse loss calculation what the appropriate normalisation is for the case when GdfidL chooses not to carry out integration along the requested displacement off the symmety axis - does transverse loss factor (V/pC/m) use distance *requested* off axis of symmetry, or *actual* distance? Appears that results are for "requested". Results are found more stable for larger cells/sigma z, results are stable to within 10% relative uncertainty using 8 cells/zigma. For mesh aspect ratio, choice will depend on model being studied to some extent. Aim is to include ABCI calculation on his parameter sweep comparisons (already includes analytic calculation) and then continue with collimators for ESA run - using default 8 cells/sigma z - and single choice of aspect ratio, and 0.3mm sigma_z. Additional parameter variations to demonstrate stability around these values can be studied after baseline predictions have been made. Noted that collimators 7 and 8 will be different to others having two different taper angles and collimator 3 will have few different flat section lengths studied, not expected to be necessary to include 1m section.

  3. Analytic calculations - spreadsheet - Nigel
    Minor changes to this to include predictions of deflection angles per unit offset of beam/collimator centre (microrad/mm). Deflections expected to be substantially smaller than in previous runs, so need to average over more bunches to achieve good resolution on kick factors. Needs stability of BPM calibration over at least the time of a signicant part of the scan. Implication for scan strategy (e.g. high statistics points throughout collimator scan, perhaps recalibration, then filling in remaining points?).

  4. Wire/bench test preparations
    Carl had noted yesterday that there was a delay in hardware fabrication required for the tests, 3-4 weeks.

  5. Progress for ESA tests
    1. Arrived safely at SLAC - 21-Mar-2006 - now with vacuum group.
    2. Sandwich modifications for the new Uk collimators are being made, Steve Molloy is taking charge of these
    3. Matlab Reconstruction code - Nigel (for Luis)
      Luis has made a first simulation of the effects of finite BPM resolution on the measurements, taking BPM z locations from optics tables (two upstream BPMs, c/o Frank J.), and of six downstream BPMs from the layout plans (therefore approx. - not from a surveyed measurement). He has assumed 1 micron rms noise on each BPM, and with 50 pulses/y position the resolution on kick factor is less good than expected, for 500/position looks OK, with relative error on kick factor (of 0.5microrad/mm) of ~10%. For this, a purely linear dependence on the kick angle as function of y was assumed for simplicity, this can be made more sophisticated (e.g. cubic near collimator wall) at later stage.
      Next steps are to include beam jitter, implemented as coherent noise assigned to all BPMs.

    4. Travellers for ESA run
      Please confirm travel plans with Mike Woods, cc: Nigel if you have not done so already. Also, could people travelling to SLAC for the run, please try to phone in to the ESA Monday meetings for the next few weeks if they do not do so already.

  6. Future plans
    There will be a (closed, management/WP/task leaders) UK meeting on 3-Apr to discuss aims for post-Apr-2007 period, with open meeting at Manchester on 24-Apr.

  7. Next meeting: date to be fixed outside meeting, suggest Thu. 20-Apr